PR11032016 o Still working on details for equipment and costs of site prep to make area larger
■ Estimated at$100,000 total cost
o Target installation date in late 2017
- Vittori Park Playground:
o Project to start in November 2016—Need to meet with neighbors
o Installation projected for late 2017
o Applied for$25,000 from CPC—Approved by City Council 10/17/16.
- Lynch Park Tot Lot(Move& Reinstall)
o Small tot lot play structure was removed to make space for the new splash pad. Tot lot will be moved to
another area next to the new large play structure.
■ Prep new area for reinstallation of tot lot—Spring 2017
■ Reinstall new tot lot—Spring 2017 (DPS/Contractor)
List of 2014 CPA Projects: All of these have been completed or are nearing completion
Park Project CPA Amount Comments
Lynch Park New bathrooms $85,000 $340K total cost(Rec $105K& Lynch
COMPLETED Trustees$150K, CPC$85)
Camp Paradise Acquire 12 acre camp from GSEM. $450,000 Acquired in July 2015 with $400,000 PARC
COMPLETED grant and $100,000 from BEV REC.
Lynch Park New playground structure $30,000 Total cost$150,000 (Funded by OCBY
COMPLETED grant and Lynch Trustees as well)
Obear Park Picnic pavilion $47,000 Completed 10/21/16
Lynch Park Carriage House feasibility study and $25,000 STILL IN PROGRESS. To be funded by CPC
preservation plan grant.
List of 2015 CPA Proigcts: All of these applications were approved by the CPC and by the City Council vote.
Park Project CPA Amount Comments
Dane Street Beach New Play Structure $60,000 $200,000 total cost(Rec $50K& Lynch
COMPLETED Trustees$20K, private fundraising$70K)
Dane Street Beach ADA Accessible Path& Beach Chairs $15,000 Total cost$20,000 (Split w/ Lynch
Trustees?) In progress
Lynch Park ADA Accessible Path& Beach Chairs $20,000 Total cost$30,000 (Split w/ Lynch
Trustees?) In progress
Cove Park New tennis courts and fencing $100,000 Total cost$160K (Private fundraising&
Lynch Trustees?) In progress
List of 2016 CPA Applications: Full applications submitted on May 6, 2016
Park Project CPA Amount Comments
Pete's Park New Play Structure/Courts&ADA $75,000 $250,000 total cost(Rec $50K& Lynch
compliance Trustees$20K, private fundraising)
Oak Heights Park New Play Structure $15,000 Total cost: $20,000 (Split w/ Lynch
Trustees?)
Vittori Park New Play Structure $20,000 Total cost: $30,000 (Split w/Lynch
Trustees?)
Cahill Park I New tennis court and fencing $50,000 Total cost: $75,000
Meeting adjourned at 8;25PM.
Respectfully submitted,
Bruce Doig, Director of Parks, Recreation&Community Services