PR10062016 o Lynch Trustees approved $10,000
o Still working on details for equipment and costs of site prep to make area 100%ADA compliant
■ Estimated at$400,000 total
o Abutters' meeting scheduled for 10/11/16 @ 7:OOPM at 17 Landers Drive
■ Abutters have been notified by Pete's Park group
o Target installation date in 2017
- Oak Heights Playground:
o Met with neighbors in June. Need to meet with group again soon to check in.
o Applied for$15,000 from CPC
o Bev Rec Park of the Year fund -$40,000
o Request$10,000 from Lynch Trustees
o Still working on details for equipment and costs of site prep to make area larger
■ Estimated at$100,000 total
o Target installation date in late 2017
List of 2014 CPA Projects: All of these have been completed or are nearing completion
Park Project CPA Amount Comments
Lynch Park New bathrooms $85,000 $340K total cost(Rec $105K& Lynch
COMPLETED Trustees$150K, CPC$85)
Camp Paradise Acquire 12 acre camp from GSEM. $450,000 Acquired in July 2015 with $400,000 PARC
COMPLETED grant and $100,000 from BEV REC.
Lynch Park New playground structure $30,000 Total cost$150,000 (Funded by OCBY
COMPLETED grant and Lynch Trustees as well)
Obear Park Picnic pavilion $47,000 To be completed SOON.
Lynch Park Carriage House feasibility study and $25,000 STILL IN PROGRESS. To be funded by CPC
preservation plan grant.
List of 2015 CPA Proigcts: All of these applications were approved by the CPC and by the City Council vote.
Park Project CPA Amount Comments
Dane Street Beach New Play Structure $60,000 $200,000 total cost (Rec $50K& Lynch
COMPLETED Trustees$20K, private fundraising$70K)
Dane Street Beach ADA Accessible Path& Beach Chairs $15,000 Total cost$20,000 (Split w/ Lynch
Trustees?) In progress
Lynch Park ADA Accessible Path& Beach Chairs $20,000 Total cost$30,000 (Split w/ Lynch
Trustees?) In progress
Cove Park New tennis courts and fencing $100,000 Total cost$160K (Private fundraising&
Lynch Trustees?) In progress
List of 2016 CPA Applications: Full applications submitted on May 6, 2016
Park Project CPA Amount Comments
Pete's Park New Play Structure/Courts&ADA $75,000 $250,000 total cost(Rec $50K& Lynch
compliance Trustees$20K, private fundraising)
Oak Heights Park New Play Structure $15,000 Total cost: $20,000 (Split w/ Lynch
Trustees?)
Vittori Park New Play Structure $20,000 Total cost: $30,000 (Split w/ Lynch
Trustees?)
Cahill Park I New tennis court and fencing $50,000 Total cost: $75,000
Meeting adjourned at 8;45PM.
Respectfully submitted,
Bruce Doig, Director of Parks, Recreation&Community Services