05-29-19 BCC Minutes - FINALCITY OF BEVERLY
PUBLIC MEETING MINUTES
SUBCOMMITTEE:
DATE:
BOARD MEMBERS PRESENT
BOARD MEMBERS ABSENT:
STAFF MEMBERS PRESENT:
OTHERS PRESENT:
RECORDER:
Conservation Commission
May 29, 2019
Chair Christine Bertoni, Vice Chair Robert Buchsbaum,
Rick Grandoni, Stephanie Herbster, Jenna Pirrotta, Bill
Squibb
David Dines
Amy Maxner, Environmental Planner
Jane Dooley
Bertoni calls the meeting to order at 7:00 p.m. at Beverly City Hall, 3r Floor Council Chamber,
Beverly, MA.
Bill Squibb acknowledged the superior work done by Conservation Agent Amy Maxner as she
moves on to a new position in another community.
REQUEST FOR CERTIFICATE OF COMPLIANCE
Cont: 100 & 102 Hull Street, DEP File #5 -1205 — construct two new single family houses
and associated appurtenances — MJP Properties, Inc. c/o Mike Panzero & Susan Purdy
The Commission would like to see a revised as -built plan and a written response to initial
comments from the site visit. Project Engineer Bob Griffin explained that all work has been done
but seed has not grown up yet and plan has been revised. Herbster moves to continue to the June
11, 2019. Seconded by Squibb. The motion carries 6 -0.
Cont: 14 Cleveland Rd. (f.k.a. 391R Elliot St.), DEP File #5 -786 — construct a single- family
home and associated site 2radin2 and utility work — William & Linda Beard
The Commission had tabled this request and asked for an RDA to formally permit the elements
that were not on the original approved plan and provide mitigation plantings and other site work
to improve issues. An RDA was submitted. The mitigation has been carried out. A site inspection
was done today and plants look good. The NDZ markers are installed, and wood pile was
removed. Trap rock is underneath the deck. Riprap has been extended from the driveway
discharge point to protect against erosion. Erosion control will remain until grass is growing.
There were no special conditions beyond the standard conditions.
Conservation Commission
May 29, 2019 Meeting Minutes
Page 2of12
Buchsbaum moves to issue a Certificate of Compliance for 14 Cleveland Road. Seconded by
Pirrotta_ The motion carries 6 -0.
Cont: 143 West Street, DEP #5 -808 - raze existing and construct new single family home
and associated appurtenances - Daniel Carnevale
The July 2001 Order governed razing the existing and construction of a new single family home
utilizing partial footprint of existing home, reconfiguration of driveway, swimming pool, deck
and associated landscaping. Work took place within 200 -Foot Riverfront Area, 100 -Foot Buffer
Zone and Bordering Land Subject to Flooding (compensatory flood storage was required). Bob
Griffin representing the applicant notes that the work has been completed with the exception of
the landscaping improvements. A site inspection was done. Also, a plan has been submitted
showing concrete paver patio being moved out of the 25' NDZ. Virginia rose and creeping
juniper plants have been added to supplement the arborvitaes as part of the mitigation plan.
Plantings will be added to the other side of the pathway.
An Enforcement Order would have to be issued to allow additional work since the Order has
expired. Squibb moves to issue an Enforcement Order to facilitate the movement of the patio and
plantings as proposed on the plan dated on May 23, 2019. Seconded by Buchsbaum. The motion
carries 6 -0. Pirrotta moves to continue to the June 11, 2019 meeting. Seconded by Squibb. The
motion carries 6 -0.
New: 400 Hale Street, DEP #5 -1070 - replace existing athletic fields with synthetic fields
and associated improvements - Endicott College
Chris Broyles, representing Meridian Associates, describes the baseball field where grass field
was replaced with synthetic field and associated improvements. Joe Orzel representing the
applicant describes mitigation plantings including NDZ restoration. The survival rate has been
good. On a slope the plantings have not survived as well (i.e., black birch and witch hazel as well
as gray dogwood). In another area there has been spotty vegetation so additional plantings are
recommended by dugout where there are better soils. In regard to water quality monitoring in
2018, some lead has been identified in some sampling. In December 2018 all samples were
clean.
Discussion addresses existing riprap slope and rework that was done. The turf field contractor
will be asked how the installation was done and what material is below the artificial turf. The
applicant's representative will investigate any drainage specifications associated with the field.
There are drainage outlets for frost protection. Herbster moves to continue to the June 11, 2019
meeting. Seconded by Pirrotta. The motion carries 6 -0.
New: 400 Hale Street, DEP #5 -1158 - construct access road and associated parking lot in
the vicinity of northeast area of the college campus - Endicott College
Conservation Commission
May 29, 2019 Meeting Minutes
Page 3 of 12
Chris Broyles of Meridian Associates, describes construction of the access road and associated
parking lot as well as invasive species management (herbicide cutting). This will continue every
5 years according to the Order of Conditions. Joe Orzel speaks to tree removal and buffer zone
trash pick -up (spring and fall). He notes that environmental signage (9 signs) has been installed.
One sign was moved due to snowplowing issue. He reports on identification of wood frog eggs
relative to enhancement of vernal pool. Also mentioned were specifics about shrub and tree
plantings. Buchsbaum moves to continue to the June 11, 2019 meeting. Seconded by Squibb.
The motion carries 6 -0.
REQUEST FOR DETERMINATION OF APPLICABILITY
New: 13 Meadow Road - expand existing rear deck and pour concrete form underneath to
support proposed storage shed - Ryan Feller
Maxner reads legal notice. Ryan Feller describes intent to expand second story deck along the
house, but no closer to the wetlands. He plans to excavate two feet below the deck so he can
install a shed foundation (18 ft. by 10 ft.) in the existing footprint. The deck steps will be moved
to the side farther away from the wetlands. Two support posts will be installed where steps are
currently located relative to shed foundation. A gravel drain edge will be installed relative to the
increase in impervious surface. Existing railroad ties will be removed. A gutter in the deck area
which will remain drains towards the retaining wall. A backhoe will be used to do half day of
work but primarily from the driveway. Removed soils will not be stockpiled.
A site visit was scheduled for Saturday, June 8, 2019 at 8 a.m. Pirrotta moves to continue until
the June 11, 2019 meeting. Seconded by Buchsbaum. The motion carries 6 -0.
New: 55 Ober Street, Lynch Park - redistribute sand washed up from 2018 storms - City of
Beverly c/o Michael Collins, Commissioner of Public Works and En2ineerin2
Maxner reads legal notice. Mike Collins describes interest in redistributing sand washed up from
storms at Lynch Park to restore access to beach for summer. Currently the sand is mounded in a
pile next to the volley ball net area, and the sand will be evenly redistributed on the landward
side of low profile seawall at Woodbury Beach. A track bobcat would be used for the work. In
addition, some long term repairs to seawall are being considered. Discussion was on practical
access to beach on concrete path which is used by pedestrians and mechanical wheelchairs.
Buchsbaum moves to issue Negative #2 and Negative #3 Determinations with condition that
sand displaced will be moved back into position over the exposed seawall. The DPW will be
working on longer term solution to problems in the area. Seconded by Herbster. The motion
carries 6 -0.
New: 11 Wirlin2 Drive - demolish existing rear deck and construct new deck, extend
driveway, remove existing and install a new shed, and perform landscape improvements -
Kenneth Walden
Conservation Commission
May 29, 2019 Meeting Minutes
Page 4of12
Maxner reads legal notice. Kenneth Walden describes intent to demolish existing rear deck and
construct new deck with precast concrete footings, extend driveway to back of house, steps will
be moved out some from house. Also proposed is to remove the existing and install a new
smaller shed further away from the edge of wetland outside both the 25' NDZ and 50' NBZ,
install a stone drip edge for capturing roof and gutter runoff and perform landscape
improvements. Maxner verified measurement of lot relative to wetland. The applicant will
remove stone dust from area where there was an above ground pool and put loam down. The
property is within the 100 foot flood plain and there is no need to grade the area. This project
will done with hand work.
Squibb moves to issue Negative 92 and Negative 43 Determinations with pervious deck addition
and no grading on site, and new shed will be shown in area as indicated on diagram. The former
shed area will be reseeded. Seconded by Buchsbaum. The motion carries 6 -0.
Recess for Public Hearings
Squibb moves to recess for public hearings. Seconded by Pirrotta. The motion carries 6 -0.
NOTICES OF INTENT /ABBREVIATED NOTICES OF INTENT /REQUESTS FOR
AMENDED ORDERS OF CONDITIONS
Cont: 7 Porter Terrace, DEP File #5 -1245 — extend Livingstone Avenue roadway and
construct new single family houses — 7 Porter Terrace, LLC c/o Brian Marks
Project engineer Bob Griffin from Griffin Engineering representing the applicant describes
proposal to extend Livingstone Avenue roadway and construct 3 new single family houses, with
associated grading, utilities and stormwater facilities. Work to take place within 100 -foot buffer
zone, 25' NDZ and 50' NBZ to bank of intermittent stream, and a waiver worksheet is included
in the NOI.
The revised plans indicate compliance with stormwater requirements. He notes that the wetland
consultant determined that there is no BVW in area of 28, 30, and 32 Ashland Street. An
intermittent stream is the only resource area, with no BVW along ditch. The Lot 4 location has
been considered relative to resource area, and a Zoning Board of Appeals waiver is being sought
regarding proposed road location. In addition, a knotweed management plan was submitted to
control invasive species.
Griffin cites current hydrologic analysis done for the area that was originally developed in 1912
and drainage improvements resulting from the proposed development. Two drywells will be
installed for controlling runoff from the proposed buildings. Dewatering will occur pushing
water away from houses. Griffin explains proposed drainage calculations relative to surcharging
and flooding of catch basins during the 50 and 100 year storms. Consequently, 18 -inch pipe will
be replaced with 24 -inch pipe to reduce risk of flooding. Riprap will be located near the
shoreline of Danvers River. A hydrant is located on Livingstone Avenue and water will be
brought into the three houses. Bituminous curbing will be used to direct water to catch basins.
Mr. Griffin has spoken with abutters regarding control of any water that would discharge onto
Conservation Commission
May 29, 2019 Meeting Minutes
Page 5 of 12
their properties. Another detail is a rain garden which is on the stormwater management plan.
Discussion ensues about how water pressure is being reduced in discharge pipe.
Peer reviewer William Ross, of New England Civil Engineering Corp., summarized actions
taken to date relative to the proposed project. He mentioned building size, driveway changes,
impact to wetland resources, and the stormwater management system. Mr. Ross outlines details
associated with impervious surface and wetlands as well as removal of sediment before
discharge. Recharge will be done with roof runoff. Drywells and rain gardens were added to
address neighbors' concern about increased runoff. It was noted that the underground storage
tank has been eliminated from the plan and an alternative solution was presented to address
potential flooding in the area and increase protection for Porter Terrace. Also mentioned was the
location for the proposed garage within the 50' NBZ. He explained details about what gutters
should be installed to address drainage. Griffin summarized the 50 and 100 year storm drainage
calculations. Ross will investigate the riprap discharge area.
Discussion addresses the three versus two lot alternative. The Commission recommends that peer
review information be relied upon when reviewing this filing. Griffin notes that there is soft
ground (likely caused by test pits and debris) and ledge in the area. Hydraulic fracturing is being
analyzed to possibly avoid blasting of ledge.
Bradley Pomereau, 36 Ashton Street, inquires about the effect of stormwater and catch basins on
existing properties and if there could be more water in their backyards. Griffin responds that
water should not pond on the neighbors' or other properties in the vicinity except in heaviest of
rainstorms. Ross concurs that this property should not incur any more water than it does
currently. Griffin outlines drainage calculations before and after proposed construction and how
the water would get pushed towards Livingston Ave.
Mr. Griffin explains where curbing would be located to push water in response to a question
from Katie Harris, 32 Ashton Street. He also explained where roof runoff would go via gutters to
the rain garden. He adds that some trees would be cut but not as many as originally proposed.
Water would continue to go toward the intermittent stream. Lynn (last name unknown), 8 Porter
Terrace, expressed concern about existing water on her property and more water being pushed
toward Porter Terrace. Griffin explains how there should be improvements to the drainage
conditions on her property. The 17 Porter Terrace resident describes how his backyard fills up
with water and how it would get pushed towards house. Griffin responds about intent to push
water towards the street. Ken St. Pierre, 16 Porter Terrace, describes how sewage at his property
has backed up. Griffin notes that this is the first time he heard of sewage problems on Porter
Terrace. This will be brought to the attention of the City's engineering department. Discussion
addresses where a berm could be continued in front of some properties.
Buchsbaum moves to close the hearing. Seconded by Squibb. The motion carries 6 -0.
New: River Street and McPherson Drive within the Bass River - perform mechanical
maintenance dred2in2 of the Bass River - City of Beverly c/o Michael P. Cahill, Mayor
Conservation Commission
May 29, 2019 Meeting Minutes
Page 6of12
Maxner reads legal notice. The consultant representing the City speaks to proposal to perform
mechanical maintenance dredging of the Bass River, and this NOI incorporates both Phase I and
Phase II that were previously permitted under two separate Orders of Conditions. The Orders
have lapsed so this is anew application for the same proposed project. All other approvals (i.e.,
Chapter 91) have been received.
The City has a grant to fund Phase II of the project. He describes mitigation associated with the
project (i.e., salt marsh improvement at Obear Park). Contamination removal work will not occur
in the National Grid area in the river until that has been completed. The Army Corps of
Engineers has tested material and deemed that it can be disposed of 10 miles off shore. Part of
the plan at Obear Park at the culvert location is to do a study of salt marsh that would allow
greater flushing and elimination of Phragmites. Department of Marine Fisheries approval would
be sought for this project. No work was done under the previous Orders which will have to be
closed out.
Discussion ensued about the width of dredging area south and north of Bridge Street relative to
commercial and recreational boat use. The last time the river was dredged was in 1955. A 10-
year maintenance dredging program was mentioned as a recommendation. The goal is to do as
much dredging as funding will allow. Discussion addresses the reason for the dredging motivated
by groundings that occur for Bass Haven Yacht Club members as well as commercial users
along the river. Work would be restricted for winter flounder and shellfish protection. The work
window is October through February. The work to be done at the salt marsh at Obear Park will
be separately permitted
Bill (last name undiscernible), expressed concern about his commercial marine use of Bass River
and maneuvering around dredging equipment. The contractor to be hired will work with
commercial users to allow access in and out of the river. Jim Butler reiterated the need for
moorings to be placed in the correct locations for large tide which occurs once a month.
Desmond Boat Yard representative inquired about details of the project in consideration of his
establishment's docking needs. The consultant responded to a question from neighbor about the
expectation of 50 days of dredging to remove 50,000 cubic yards of material. Work schedules
would be dictated by tides. A crane will be used and sometimes an excavator.
Squibb moves to close the hearing. Seconded by Buchsbaum. The motion carries 6 -0.
Reconvene the Regular Meeting
Herbster moves to reconvene the regular meeting. Seconded by Pirrotta. The motion carries 6 -0.
OLD/NEW /OTHER BUSINESS
Cont: Beverly Airport — update on Airport Vegetation Management Program — Airport
Solutions Group /Airport Manager
The airport manager is reviewing the Commission's schedule to determine what upcoming
meeting she could attend.
Conservation Commission
May 29, 2019 Meeting Minutes
Page 7of12
New: 43 Haven Way, DEP File #5 -1193 — request for extension to Order of Conditions —
Olaf Stellin2
The Order, issued in October 2016 governs demolition of the existing and reconstruction of a
new garage, construct new sunroom off rear of existing house and realign and modify driveway
layout and surfaces, install low- profile retaining wall, and other ancillary house renovations
(windows, siding). Work to take place within 100 -foot buffer zone to top of coastal bank and
200 -foot Riverfront Area.
Squibb moves to issue a 1 -year extension under the Wetlands Protection Act and Beverly's local
Ordinance. Seconded by Herbster. The motion carries 6 -0.
New: 43 Haven Way, DEP File #5 -1193 — request for minor modification to Order of
Conditions — Olaf Stellin2
The project was analyzed and determined that there is no longer a need to remove garage. A
small extension will be done behind the garage to accommodate two cars. Mitigation is proposed
for 98 square feet in the 25' NDZ and a 4:1 offset will be done by reducing part of the driveway
pavement. Roof runoff will be tied into an existing pipe.
Pirrotta moves to approve a Minor Modification as presented. Seconded by Squibb. The motion
carries 6 -0.
New: 95 Sam Fonzo Drive, DEP File #5 -949 — request for extension to Order of Conditions
— Scott Haenssler, The Coastal Group
Daniel Simonelli representing the applicant speaks to request an extension to complete the
project (remaining drainage) with no changes to plans or conditions, after discussions with
consultant, FAA, and the Planning Board. The project was started in the fall and stopped due to
winter conditions. A retaining wall with fabric is in place, the pond has been carved out, and
remaining catch basins are being installed. Maxner notes that the site is stable, erosion control
has been reinstalled, and wetland flagging is re- installed. The retaining wall that was required
before any other work was started was installed and it serves well for erosion control. Work on
the detention basin will require dewatering plan which will be provided to the Commission.
Pirrotta moves to approve the extension to August 2, 2020. Seconded by Squibb. The motion
carries 6 -0.
New: 54 Oak Street and 142 & 150 Valley Street - request to modify Determination of
Applicability — Sunfield Condominium Trust c/o Michael Milsom, Trustee
Conservation Commission
May 29, 2019 Meeting Minutes
Page 8of12
Michael Milsom describes details about a request to remove trees that posed a danger to
neighboring properties. He mentions interest in removing recent downfall of limbs and new cut
wood. Maxner concurred. The arborist left some trees at varying heights. He adds that there is
interest in reducing the size of some of these remaining cut trees. Work was done on more than 6
trees in response to concern from neighbors. Discussion was on what native species could be
planted, as well as how handwork could be done for the remaining work. Discussion addresses
how the fall would be a good time for work to occur when area isn't so wet.
Buchsbaum moves to modify the Determination of Applicability. Seconded by Herbster. The
motion carries 6 -0.
New: 20,30 & 40 Webster Avenue, DEP File #5 -1237 — EO cart path restoration follow up
discussion — PD Development
Maxner reports on meeting with developer. The Commission notes that restoration of the cart
path resembles a driveway versus cart path. Bob Griffin representing the applicant describes how
processed gravel is what was put down, according to the approved plan. The developer could add
soil and seed as well as rocks. Discussion addresses if access for the abutter would be allowed on
a regular basis on the traveled cart path, and if crushed stone would be a better surface. The cart
path is intended for pedestrian use. Maxner opined that the material used there is not appropriate
and suggests it should be removed and shoulders rerolled. Griffin emphasizes that the cart path
has always had a road base. Discussion ensues about how the path is compacted and if 5 to 6 feet
width of material could remain with loamed shoulders. Also suggested was to remove the road
base that was added. The Commissioners will independently visit the site.
Herbster moves to delay the deadline of June 7, 2019 for final restoration, and continue to the
June 11, 2019 meeting. Seconded by Squibb. The motion carries 6 -0.
New: Expenditure Approvals
Squibb moves to pay mileage reimbursement to Amy Maxner $41.85 for mileage reimbursement
for the month of May 2019 while carrying out site visits and other Conservation Commission
business. (93 miles x .45 cents = $41.85). Seconded by Buchsbaum. The motion carries 6 -0.
Order of Conditions
7 Porter Terrace
Discussion ensues about Standard Conditions and the following Special Conditions under the
Act:
1. The applicant /project proponent shall submit a separate Notice of Intent for work
involved in off -site drainage improvements.
Conservation Commission
May 29, 2019 Meeting Minutes
Page 9of12
2. Prior to work commencing, all trees slated for preservation shall be conspicuously
flagged in the field and said flagging inspected by the Conservation Agent.
3. Invasive species removal, debris and trash removal shall be undertaken prior to work
commencing and completion of these tasks shall be verified by the Conservation
Commission or its designee.
4. All proposed houses shall be equipped with roof leaders /gutters which shall be directly
connected to proposed drywells and /or rain garden. This is a requirement of approval. A
revised plan shall be submitted prior to work that reflects additional curbing as described
above.
5. Roadway curbing shall be extended west along the proposed improved section of
Livingstone past the frontage of 17 Porter Terrace.
6. Driveway curbing shall be extended along the northerly edge of the driveway servicing
Lot 4 (labeled 9100 Livingstone on plan).
7. A revised plan shall be submitted prior to work that reflects additional curbing as
described above in Special Condition 94 and 95.
8. All proposed catch basins shall be deep sump style.
9. All stormwater BMP's shall be constructed and installed per the manufacturer's
specifications.
10. The proposed depression, berm, granite curb wear and associated drainage pipe at the
north east of Lot 4 shall be constructed to specifications.
11. The proposed rain garden shall be properly maintained in perpetuity, including weeding,
replacing dead vegetation, inspecting soil for erosion and re- mulching void areas. This
obligation shall be expressed in all deeds to succeeding owners or portions of the
property. This condition shall survive in perpetuity beyond the issuance of a Certificate of
Compliance.
12. Monitoring of the stormwater BMP's and final discharge points shall be undertaken for 1
year post construction after storm events of 10 -year intensity or greater.
13. The Operation & Maintenance of all stormwater BMP's shall be adhered to, and all
maintenance and inspection reports per the Stormwater Operation and Maintenance Plans
shall be submitted to the Conservation Agent on an annual basis no later than December
31S of each year. This condition shall run in perpetuity beyond the issuance of a
Certificate of Compliance.
Buchsbaum moves to issue an Order of Conditions under the Wetlands Protection Act. Seconded
by Squibb. The motion carries 6 -0.
Discussion ensues about property lines, setbacks, and frontage relative to Zoning Board of
Appeals approval, as well as the need to address other alternatives that would allow the work to
occur outside the 50' NBZ.
Buchsbaum moves to deny the project under the local Ordinance because it is encroaching on the
50 foot NBZ and mitigation is not adequate and the applicant did not meet the burden of proof to
show that there are no feasible or practicable alternatives. Seconded by Herbster. The motion
carries 6 -0.
Conservation Commission
May 29, 2019 Meeting Minutes
Page 10 of 12
River Street and McPherson Drive within the Bass River
The Commission mentions adopting the previous approved conditions and requiring a separate
filing for Obear Park salt marsh restoration and mitigation. Discussion was on how the
contractors need to coordinate with the City relative to commercial use and access /mooring
issue.
Discussion ensues about Standard Conditions and the following Special Conditions under the
Act and local Ordinance:
Pha-,e 1
1. Prior to commencing any activity, a schematic of all proposed construction controls
including dewatering, erosion control and silt boom installation shall be provided to the
Conservation Administrator for the record.
2. Recommendations contained in the February 28, 2012 comment letter from Division of
Marine Fisheries are incorporated herein and made part of the Order of Conditions.
These recommended conditions include:
a. All dredge footprints shall be marked in the field using GPS coordinates and
buoys placed at the surface as a guide for the contractor during dredge activities;
b. A time of year restriction prohibiting work between February 15 and June 30 of
any year shall be enforced to protect winter flounder spawning and juvenile
development;
c. To mitigate the loss of Land Containing Shellfish (which includes both Phase I
and Phase II impacts), an area of 95,000 square feet of shellfish re- seeding shall
be implemented with guidance from and coordination with the Division of Marine
Fisheries.
d. Stormwater quality /treatment improvements are recommended, and are in part
addressed in Special Condition 4 3 below:
3. Prior to the issuance of a Certificate of Compliance, the following stormwater Best
Management Practices, as part of planned management activities intended by the City
Department of Public Services, shall be implemented at the City DPW Garage/Yard
located at 148 Park Street:
a. The materials stockpile bays (which store discarded asphalt, catch basin and street
sweeping spoils and other materials) shall be equipped with a roof system to
shelter the materials from direct contact with rain and snow, therefore decreasing
the amount of runoff coming from the bays;
b. The catch basin immediately downstream from these bays, which connects to
drainage that discharges to the Bass River, will be upgraded with a stormwater
treatment device (Vortechnix Unit, Stormceptor or equivalent) to achieve
improved TSS removal and water quality treatment;
c. During the appropriate seasons, a street sweeper is reported to be operational on a
daily basis at some location in the City, and it is proposed to have the sweeper
sweep the DPW yard daily after coming back from its route — this schedule may
be modified to not less than once per week.
Conservation Commission
May 29, 2019 Meeting Minutes
Page 11 of 12
4. Prior to commencing dredging activities, a copy of any and all protocol and /or
monitoring plans (as required by DEP, ACOE and that resulting from any required
habitat restoration program) shall be submitted to the Commission for review and record.
5. Wherever possible, during dredging activities, surface debris (i.e. bikes, shopping carts
etc...) shall be removed manually and disposed of properly. Should such debris fall
outside of the dredging footprint, an effort shall be made to reach the material small boat
or dinghy and taken out by hand with minimal disturbance to the substrate.
Pha-,e 2
6. Prior to commencing any activity, a schematic of all proposed construction controls
including dewatering, erosion control and silt boom installation shall be provided to the
Conservation Administrator for the record.
7. Recommendations contained in the May 19, 2015 comment letter from Division of
Marine Fisheries and Bourne Consulting email response of even date are incorporated
herein and made part of the Order of Conditions. * *See Attached **
8. Prior to the issuance of a Certificate of Compliance, the following stormwater Best
Management Practices, as part of planned management activities intended by the City
Department of Public Services, shall be implemented at the City DPW Garage/Yard
located at 148 Park Street:
a. The materials stockpile bays (which store discarded asphalt, catch basin and street
sweeping spoils and other materials) shall be equipped with a roof system to
shelter the materials from direct contact with rain and snow, therefore decreasing
the amount of runoff coming from the bays;
b. The catch basin immediately downstream from these bays, which connects to
drainage that discharges to the Bass River, will be upgraded with a stormwater
treatment device (Vortechnix Unit, Stormceptor or equivalent) to achieve
improved TSS removal and water quality treatment;
c. During the appropriate seasons, a street sweeper is reported to be operational on a
daily basis at some location in the City, and it is proposed to have the sweeper
sweep the DPW yard daily after coming back from its route — this schedule may
be modified to not less than once per week.
9. Prior to commencing dredging activities, a copy of any and all protocol and /or
monitoring plans (as required by DEP, ACOE and that resulting from any required
habitat restoration program) shall be submitted to the Commission for review and record.
10. Wherever possible, during dredging activities, surface debris (i.e. bikes, shopping carts
etc...) shall be removed manually and disposed of properly. Should such debris fall
outside of the dredging footprint, an effort shall be made to reach the material small boat
or dinghy and taken out by hand with minimal disturbance to the substrate.
Buchsbaum moves to issue an Order of Conditions for the Bass River dredging. Seconded by
Squibb. The motion carries 6 -0.
New: Other
Conservation Commission
May 29, 2019 Meeting Minutes
Page 12 of 12
Maxner describes a resident request (address not provided) for a building permit to reconstruct a
deck (4 feet larger from house toward the wetland 40 feet away) with 2 footings to be hand dug.
Stairs will remain in the same location. The project should be addressed by the Commission via
an RDA, instead of a Minor Project Permit.
Adjournment
Herbster moves to adjourn at 11:32 p.m. Seconded by Pirrotta. The motion carries 6 -0. The next
regular meeting of the Conservation Commission is Tuesday, June 11, 2019 at Beverly City Hall,
3rd Floor Council Chamber.